CENTRAL ELEMENTARY -- ROOF REPLACEMENT

April 5, 2017

May 1, 2017

1:00 PM

The Marshall County Board of Education requests professional services from a contracting/roofing firm for the roof replacement project at Central Elementary School.

The Firm will provide all material, labor, equipment, and insurances necessary to perform the following scope of work:

Scope of Work – Approximately 32,300 square feet

  1. Remove the existing roof system down to the deck.
  2. Provide and install 4” of new polyisocyanurate roof insulation.
  3. Provide and install new tapered polyisocyanurate roof insulation around roof drains.
  4. Provide and install a new .060 fully adhered EPDM rubber roofing system.
  5. Flash watertight all existing roof penetrations.
  6. Fabricate and install a new metal trim around the perimeter of the roof areas.
  7. Provide a 20 year manufacturer’s warranty upon completion of the project.
  8. All work will be completed within strict accordance to the manufacturer’s specifications.
  9. Organize and clean-up project at the completion of each day.
  10. All debris will be removed from site and hauled to an approved landfill at the completion of the project.

Scope of Work – Approximately 11,600 square feet

  1. Remove the existing EPDM membrane, leaving the existing polyisocyanurate roof insulation in place.
  2. Provide and install a new ½” coverboard over the existing polyisocyanurate roof insulation.
  3. Provide and install new .060 fully adhered EPDM rubber membrane.
  4. Flash watertight all existing roof penetrations.
  5. Fabricate and install a new metal trim around the perimeter of the roof areas.
  6. Provide a 20 year manufacturer’s warranty upon completion of the project.
  7. All work will be completed within strict accordance to the manufacturer’s specifications.
  8. Organize and clean-up project at the completion of each day.
  9. All debris will be removed from site and hauled to an approved landfill at the completion of the project.

All work can begin by May 29, 2017.  Work must be completed no later than August 15, 2017.

          

CAMERON ELEMENTARY -- PAVING PROJECT

April 11, 2017

May 4, 2017

10:00 AM

Paving three parking lots at Cameron Elementary School.

Site inspection meeting shall be held:  Thursday, April 27, 2017 @ 1:00 PM at Cameron Elementary School, 12 Church Street, Cameron, WV 26033.

The work would involve 4: rotomilling, the removal of the existing surface and repaving with 4" hot mix asphalt consisting of a base/leveling course and a wearing surfact rolled in place complete over approximately 8,100 square feet and the remaining area of approximately 1,836 square feet light milled and paved with 2"asphalt rolled in place complete, and pave to raise the low area at the rear alley where water is standing.

The work to be performed under this contract shall be fully completed on or before August 9, 2017.

 

 

CLICK HERE FOR FULL SPECS: Cameron Elementary specifications for paving